Fit-Out of a retail extra unit – Watford Client Tesco Stores Limited Main Contractor Uplands Value Fit Out Cost £10m Project Duration 10 Weeks Gleave Partnership Role Project Managers & Monitoring Consultants Major Fit out of an existing Flagship Tesco Extra with a gross floor area of of 130,000 sq ft and net sales area […]
Read More
Mansfield Leisure Centre Client Mansfield District Council Main Contractor Taylor Woodrow Construction Limited Value £3.70m Project Duration 27 Weeks Gleave Partnership Role Quantity Surveyors The project comprised the construction of a new leisure facility for Mansfield District Council. The scheme provided a main hall which could be used for basketball, indoor football, badminton and also […]
Ellesmere, Hawnthorn Road Client Tesco Stores Limited Main Contractor Longcross Group Limited Value £5,901,802 Project Duration 26 weeks Gleave Partnership Role Cost Manager The works comprise the construction of an environmental superstore with 21,000 sq. ft. net sales area. The store incorporates a timber frame, sustainable cladding, rainwater harvesting and rooflights. All together with associated […]
Ambient Distribution Centre – Magor Client Tesco Stores Limited Main Contractor Britannia Construction Ltd Value £22 million Project Duration 34 Weeks Gleave Partnership Role Cost Managers / Quantity Surveyors Construction of 265,000 sq ft Ambient Trunking Station, including all associated Yards, Car Parks, and Off-Site Hughways works. Building comprising piled foundations, and raised internal floor; […]
Ambient Distribution Centre – Donabate Client Tesco Ireland Limited Main Contractor J. Manning & Son (Dublin) Ltd Value €68.20 million Project Duration 56 Weeks Gleave Partnership Role Cost Managers / Quantity Surveyors The Works comprise the construction of a 740,000 sq. ft. Warehouse building; Associated Main Offices internally at mezzanine level; Goods-in and Goods-out Offices; […]
Ambient Distribution Centre – Lichfield Client Tesco Stores Limited Main Contractor GMI Construction Group PLC Value Fit-Out Works – £12.50m; Shell Construction – £20m Project Duration Overall – 37 Weeks; Fit-Out – 28 Weeks; Gleave Partnership Role Cost Managers / Quantity Surveyors Fit-Out works to 650,000 sq ft Ambient Distribution Centre, comprising all Mechanical, Electrical […]
Portal Waste Mixed Use Client Tesco Stores Limited / Spen Hill Developments / Santon Group Main Contractor Simons Construction Limited Value Project Value – £104m Project Duration Land Reclamation – 12wks; Phase 1 – 39wks; Procurement Competitive Tender with second stage negotiation Gleave Partnership Role Cost Managers / Quantity Surveyors / Employers Agent A major […]
Automated Ambient High Bay Distribution Centre – Middlesbrough Client Tesco Stores Limited Main Contractor Bowmer & Kirkland Limited Value Build Cost – £70m; Automation – £35m Project Duration Overall – 82 Weeks (including 2 Sectional handovers and commissioning); Procurement Competitive Tender Gleave Partnership Role Cost Managers / Quantity Surveyors Shell and full Fit-Out works for […]
Ambient Distribution Centre – Reading Client Tesco Stores Limited / Spen Hill Developments Limited Main Contractor Vinci Construction (UK) Limited Value Build Cost – £44m (Separate Main Contracts for Shell and Fit-Out and Directly employed specialists) Procurement Competitive Tender Gleave Partnership Role Employers Agent / Cost Managers / Quantity Surveyors Shell and full Fit-Out works […]
We are delighted to announce that Jack Cawthra has joined the Gleave Team, based in Northwich, we wish Jack well in his new role.