Automated Ambient High Bay Distribution Centre - Middlesbrough

Client Tesco Stores Limited
Main Contractor Bowmer & Kirkland Limited
Value Build Cost - £70m; Automation - £35m
Project Duration Overall – 82 Weeks (including 2 Sectional handovers and commissioning);
Procurement Competitive Tender
Gleave Partnership Role Cost Managers / Quantity Surveyors
Date Overall Completion – March 2010

Shell and full Fit-Out works for a 900,000 sq ft fully automated ambient High Bay Distributiion Centre, comprising 500,000 sq ft Low Bay and 400,000 sq ft High Bay Warehouse.

Construction of Vehicle Maintenance Building including all Installations, Specialist Fit-Out and provision of Offices; External Works, including Yards; Car-Parks; Fuel Island, Wash Facilities, Weighbridge, Automated Site Security and Access Equipment; Off-Site Highways, and Drainage installations; Incoming Mains Services installations.